NAMA : christovao j. s. (juffrez)
NPM : 07310004
PROG.STUDI : TEKNIK SIPIL
1. Rancangan Imput MS.Project pada pembangunan Rumah Tinggal Type 45.
Tabel. View Ghantt Chart
No | Task Name | Durasi | Star | Finish | Prodecessor |
1 | Pekerjaan Persiapan | 3d | 11/6/2009 8:00 | 11/10/2009 17:00 | |
2 | Persiapan lokasi | 1d | 11/6/2009 8:00 | 11/6/2009 17:00 | |
3 | Pasang bouwplank | 1d | 11/6/2009 8:00 | 11/6/2009 17:00 | |
4 | pembersihan | 1d | 11/6/2009 8:00 | 11/6/2009 17:00 | |
5 | Pekerjaan pondasi | 11d | 11/6/2009 8:00 | 11/20/2009 17:00 | |
6 | Pengalian pondasi | 2d | 11/6/2009 8:00 | 11/9/2009 17:00 | |
7 | pasangan batu kosong | 2d | 11/6/2009 8:00 | 11/9/2009 17:00 | |
8 | pasir pasang | 2d | 11/6/2009 8:00 | 11/9/2009 17:00 | |
9 | pondasi batu kali | 3d | 11/6/2009 8:00 | 11/10/2009 17:00 | |
10 | pekerjaan tanah urgan | 2d | 11/6/2009 8:00 | 11/9/2009 17:00 | |
11 | Pekerjaan Beton | 6d | 11/6/2009 8:00 | 11/13/2009 17:00 | |
12 | Sloof 15/20 | 3d | 11/6/2009 8:00 | 11/10/2009 17:00 | |
13 | Kolom praktis 15/15 | 3d | 11/6/2009 8:00 | 11/10/2009 17:00 | |
14 | Pekerjaan Rng Balk 15/20 | 4d | 11/6/2009 8:00 | 11/11/2009 17:00 | |
15 | Pekerjaan pasangan /Dinding | 20d | 11/6/2009 8:00 | 12/3/2009 17:00 | |
16 | Pas.Batu bata | 7d | 11/6/2009 8:00 | 11/16/2009 17:00 | |
17 | Pek.Plesteran | 5d | 11/6/2009 8:00 | 11/12/2009 17:00 | |
18 | Pek.Acian | 5d | 11/6/2009 8:00 | 11/12/2009 17:00 | |
19 | Pekerjaan Kayu | 9d | 11/6/2009 8:00 | 11/18/2009 17:00 | |
20 | Kusen Pintu & Jendela | 5d | 11/6/2009 8:00 | 11/12/2009 17:00 | |
21 | Pasangan Kaca | 1d | 11/6/2009 8:00 | 11/6/2009 17:00 | |
22 | Pek.Atap | 5d | 11/6/2009 8:00 | 11/12/2009 17:00 | |
23 | Pekerjaan Kuda-Kuda | 1d | 11/6/2009 8:00 | 11/6/2009 17:00 | |
24 | Pek.Usuk dan Reng | 2d | 11/6/2009 8:00 | 11/9/2009 17:00 | |
25 | Pek.Genteng | 2d | 11/6/2009 8:00 | 11/9/2009 17:00 | |
26 | Pekerjaan Lantai | 4d | 11/6/2009 8:00 | 11/11/2009 17:00 | |
27 | pas keramik polos 30x30 | 3d | 11/6/2009 8:00 | 11/10/2009 17:00 | |
28 | Pas. Km/Wc 20x20 (lantai & dinding ) | 1d | 11/6/2009 8:00 | 11/6/2009 17:00 | |
29 | Pekerjaan Sanitasi & Drainase | 27d | 11/6/2009 8:00 | 12/14/2009 17:00 | |
30 | Septictank & peresapan | 2d | 11/6/2009 8:00 | 11/9/2009 17:00 | |
31 | Pempipaan | 3d | 11/6/2009 8:00 | 11/10/2009 17:00 | |
32 | Pas.Kloset & Kran | 1d | 11/6/2009 8:00 | 11/6/2009 17:00 | |
33 | Pekerjaan Instalasi | 6d | 11/6/2009 8:00 | 11/13/2009 17:00 | |
34 | Pek.Titik lampu | 2d | 11/6/2009 8:00 | 11/9/2009 17:00 | |
35 | Pek.Elektrikal | 1d | 11/6/2009 8:00 | 11/6/2009 17:00 | |
36 | Pek.Plafond | 9d | 11/6/2009 8:00 | 11/18/2009 17:00 | |
37 | Pekerjaan Rangka Plafond | 4d | 11/6/2009 8:00 | 11/11/2009 17:00 | |
38 | Pas.Eternit | 3d | 11/6/2009 8:00 | 11/10/2009 17:00 | |
39 | Pekerjaan Finishing | 9d | 11/6/2009 8:00 | 11/18/2009 17:00 | |
40 | Pengecetan | 4d | 11/6/2009 8:00 | 11/11/2009 17:00 | |
41 | Masa perawatan | 5d | 11/6/2009 8:00 | 11/12/2009 17:00 | |
Tabel. View Resource Sheet
No | Resource Name | Type | Material Label | Initial | Max Unit | Std Rate (Rp) | Over rate (Rp) | Cost Use (Rp) | Accrue At | Base Calender |
1 | Mandor | Work | | M | 100 % | 4,000.00 | | | | standard |
2 | Tk.Batu | Work | | TB | 500% | 2,500.00 | | | | standard |
3 | Tk.Kayux | Work | | TK | 400% | 3,500.00 | | | | standard |
4 | Pekerja | Work | | P | 400% | 2,500.00 | | | | standard |
5 | Tk. Listrik | Work | | T.List | 100% | 0.00 | | | star | standard |
6 | Semen/PC | Material | Sak | SM | | 28,5000.00 | | | star | |
7 | Kapur | Material | m3 | KP | | 48,000.00 | | | star | |
8 | Pasir | Material | m3 | PS | | 70,000.00 | | | star | |
9 | Batu kali | Material | m3 | B. Kl | | 45,000.00 | | | star | |
10 | Batu Pecah | Material | m3 | B.PC | | 125,000.00 | | | star | |
11 | Batu Bata | Material | Bh | B.bt | | 300 | | | star | |
12 | Paving Blok | | Bh | PV | | | | | star | |
13 | Keramik 30/30 | Material | m2 | K 30 | | 47,000.00 | | | star | |
14 | Keramik 20/20 | Material | m2 | K 20 | | 29,000.00 | | | star | |
15 | Cat tembok | Material | gln | C.Tmb | | 28,000.00 | | | star | |
16 | Cat kayu | Material | Kg | C.Ky | | 15,000.00 | | | star | |
17 | Paku | Material | Kg | Pk | | 6,500.00 | | | star | |
18 | Kayu Balok | Material | m3 | K.Bl | | 1,300,000.00 | | | star | |
19 | Kayu Usuk | Material | m3 | K.Us | | 800,000.00 | | | star | |
20 | Kayu Reng | Material | m3 | K.Re | | 430,000.00 | | | star | |
21 | Genteng | Material | m2 | Gt | | 35,000.00 | | | star | |
22 | Eternit | Material | m2 | Et | | 36,000.00 | | | star | |
23 | Kaca 5 mm | Material | | Kc | | 37,500.00 | | | star | |
24 | Engsel & Grendel | Material | bj | Eng | | 9,000.00 | | | star | |
25 | Handle dan Pengunci | Material | bj | Han | | 15,500.00 | | | star | |
26 | Besi Tulang | Material | Btang | B.Tl | | 65,000.00 | | | star | |
27 | Kawat | Material | ml | Kwt | | 15,000.00 | | | star | |
28 | Angkur | Material | bj | Ang | | 7,500.00 | | | star | |
29 | Lampu Bohlam | Material | bj | L.B | | 36,000.00 | | | star | |
30 | Lampu neon | Material | bj | L.N | | 18,000.00 | | | star | |
31 | Kran | Material | bj | Kr | | 25,000.00 | | | star | |
32 | Pipa PVC | Material | ml | PVC | | 45,000.00 | | | star | |
33 | Kloset | Material | bj | Kls | | 125,000.00 | | | star | |
34 | Plamir | Material | Kg | Plamir | | 7,500.00 | | | star | |
35 | Amplas | Material | lbr | Amp | | 3,500.00 | | | star | |
2. VISI MISI FAKULTAS TEKNIK 2014
Visi Fakultas Teknik :
Sebagai fakultas yang bermutu dan bermartabat dlam pelaksanaan Tridharma Perguruan Tinggi untuk mencapai kepuasan pemangku kepentingan.
Misi nFakultas Teknik :
1. Melaksanakan sistim manajemen mutu sebagai landasan tata kelola dalam penguatan manajemen guna menjamin terlaksananya Tridharma perguruan tinggi yang bermutu.
2. Melaksanakan Komitmen sebagai pelayan mutu untuk mencapai standar mutu yang ditetapkan dan diisyaratkan oleh pemangku kepentingan dalam setiap kegiatan Tridharma perguruan tinggi.
3. Mengembangkan sumber daya manusia yang bermutu dan bermartabat.
4. Menerapkan dan mengembangkan IPTEK, kemempuan berwirausaha, keahlian, dan etika professional, etika kecendekiawan dan berwawasan lingkungan sebagai produk unggulan melalui kegiatan Tridharma perguruan tinggi.
5. Meningkatkan dan mengembangkan pelaksanaan Tridharma perguruan tinggi yang bermutu, bermatabat dan berkelanjutan.
Program Studi Teknik Sipil :
- menjadi teknik sipil yang unggul dan sebagai pusat rujukan pemanku kepentingan dalam bidang rekayasa sipil
- menghasilkan lulusan yang
· bermutu dan bermartabat
· mampu menerapkan dan alhi pengetahuan di bidang rekayasa teknik sipil
· mampu merencanakan, melaksanakan, mengawasi dan mengevaluasi pelakasanaan pekerjaan sipil dengan pemanfaatan teknologi informasi yang berwawasan lingkungan
· mampu meningkatkan dan mengembangkan diri dalam pendidikan yang berkelanjutan dengan prinsip belajar seumur hidup
· mampu bekerja sama, membangun komuniksi dan jejaring tingkat nasional m aupun internasional
· memiliki etika kecendikiawanan, kemampuan berwirausaha dan berwawasan lingkungan yang memenuhi kepuasan pemangku kepentingan
- berperang serta dalam pembangunan yang bermanfaat bagi masyarakat